Drawing of Record Submitted |
7/20/2009..revised 7/272009....7/28 |
Electronic Drawing |
7/20/2009..revised 7/27/2009..7/28 |
Final Grading Report |
7/17/2009 |
Date Scheduled |
7/21/2009 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
7/22/2009 Approved per Dennis Wright
6/3/2010 Approved per Dennis Wright.. 1 year warranty |
Water |
7/23/2009 Corrections required per Kevin Condie.. Clean & paint hydrant, check wire
8/3/2009 Approved per Kevin Condie
6/15/2010 Approved per Tim. 1 year waranty wire good |
Wastewater |
7/23/2009 Corrections required per Kevin Condie.. Clean & paint hydrant, check wire
8/3/2009 Approved per Kevin Condie
6/15/2010 Approved per Tim. 1 year waranty wire good |
Engineering |
7/23/2009 Correctins required per Brandon Wright.. Monuments not stamped, road not built per plan between Phase 2 & 3, grading report not correct
7/28/2009 Approved per Brandon Wright |
City Development Engineer |
7/21/09 corrections required per Cathy H. Electronic DWG of record missing sewer lateral tie to last lot on North side of road. Missing call on street light by knuckle on North side of roadway. Per Ken B. Street light is missing. End of road markers are missing. Excavation still in process. Still stacking rock walls. Heavy equipment still on site. Rock piles still in street.
7/27/09 corrections required per Cathy H. Need private improvement development certificate, hillside compliance letter, rock wall certifications.
7/31/2009 Approved ..Cathy H
6/4/10 - 1 year warranty approved per Ken B |
Landscaping |
7/28/09 approved per Cathy H. Provide revised landscape plan for approval. Required street trees and streetscape landscaping will be completed for each individual residence at residence construction. Landscape inspection will be required for final shell inspection.
6/4/10 - 1 year warranty approved per Ken B |
| |
General Comments: |
|