Drawing of Record Submitted |
1/14/2012 |
Electronic Drawing |
1/14/2012 |
Final Grading Report |
|
Date Scheduled |
|
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
2/15/2012 Approved per Dennis Wright |
Water |
2/16/2012 Corrections required per Kevin Condie..No concrete around meter boxes, no rebar thru box,no concrete around Fire Hydrant. Need copy of recored easement
2/17/2012 Approved per Kevin Condie |
Wastewater |
2/16/2012 Corrections required per Kevin Condie..No concrete around meter boxes, no rebar thru box,no concrete around Fire Hydrant. Need copy of recored easement
2/17/2012 Approved per Kevin Condie |
Engineering |
2/16/2012 Approved per Lonnie Sullivan |
City Development Engineer |
2/15/12 approved per Wes Jenkins. |
Landscaping |
2/15/12 approved per Wes Jenkins. |
| |