[Parke Cox Trucking]
Number: Grading-42673

Drawing of Record Submitted 09/27/2011
Electronic Drawing 09/27/201
Final Grading Report 09/27/2011
Date Scheduled 09/29/2011
BUILDING PERMIT RELEASE APPROVALS
Power
Water
Wastewater
Engineering
City Development Engineer
Landscaping
FINAL INSPECTION RELEASE APPROVALS
Power
Water 9/29/11 corrections required per Kevin C. Need copy of recorded easement. Need to check valves, all need to be open. Clean and paint hydrants. Wire ok. 9/30/11 corrections required per Kevin C. Complete punch list. 9/30/2011 Approved per Barry Barnum 8/13/12 - 1 year warranty - approved per Kevin C.
Wastewater 9/29/11 corrections required per Kevin C. Need copy of recorded easement. Need to check valves, all need to be open. Clean and paint hydrants. Wire ok. 9/30/11 corrections required per Kevin C. Complete punch list. 9/30/2011 Approved per Barry Barnum 8/13/12 - 1 year warranty - approved per Kevin C.
Engineering 09/30/2011 Approved per Brandon Wright 8/03/2012 Approved per Brandon Wright.. 1yr warranty
City Development Engineer 10/03/2011 per Brett Bingham 8/03/2012 Approved per Brandon Wright.. 1yr warranty
Landscaping 09/30/2011 Approved per Brandon Wright 8/02/2012 Approved per Brandon Wright.. 1 yr warranty
    
General Comments: