[Crosby/Confluence Trailhead]
Number: Grading-42875

Drawing of Record Submitted 8/05/2011
Electronic Drawing 08/05/2011
Final Grading Report 7/15/2011
Date Scheduled 7/26/2011
BUILDING PERMIT RELEASE APPROVALS
Power
Water
Wastewater
Engineering
City Development Engineer
Landscaping
FINAL INSPECTION RELEASE APPROVALS
Power 7/26/2011 Approved per Dennis Wright 12/9/12 - 1 year warranty - approved per Dennis W.
Water 8/2/11 corrections required by Kevin C. Need to raise meter box and setter to city standards. May have to raise hydrant if bottom flange is below top of curb and put concrete around both to city standards. 9/27/11 corrections required per Kevin C. Need arrow and line size in valve collar. clean and paint hydrant - has concrete on it. 10/24/11 corrections required. Need to finish punch list. 12/12/2011 Approved per Kevin Condie 11/05/2012 Approved for 1 yr Warranty per Kevin Condie
Wastewater 8/2/11 corrections required by Kevin C. Need to raise meter box and setter to city standards. May have to raise hydrant if bottom flange is below top of curb and put concrete around both to city standards. 9/27/11 corrections required per Kevin C. Need arrow and line size in valve collar. clean and paint hydrant - has concrete on it. 10/24/11 corrections required. Need to finish punch list. 12/12/2011 Approved per Kevin Condie 11/05/2012 Approved for 1 yr Warranty per Kevin Condie
Engineering 7/27/2011 Approved per Brandon Wirght 10/11/12 - 1 year warranty - approved per Brandon Wright.
City Development Engineer 7/27/11 corrections required per Brett B. Asphalt not in. Curb and gutter not done. No landscaping. 7/28/11 NA per Brett B. 10/11/12 - 1 year warranty - approved per Brandon Wright.
Landscaping 7/27/11 corrections required per Brett B. Asphalt not in. Curb and gutter not done. No landscaping. 7/28/11 NA per Brett B. 10/11/12 - 1 year warranty - approved per Brandon Wright.
    
General Comments: