Drawing of Record Submitted |
3/27/2012 |
Electronic Drawing |
3/27/2012 |
Final Grading Report |
3/28/2012 |
Date Scheduled |
3/29/2012 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
3/29/12 approved per Dennis W.
2/6/13 - 1 year warranty - approved per Dennis W. |
Water |
4/02/2012 Corrections required per Kevin Condie.. Concrete around valve's meter box, check wire
4/09/2012 Corrections required per Kevin Condie..Clean and paint turn hydrant, no rebar through box, Fire line valve need to be turned
4/17/12 approved per Kevin C.
3/05/2013 Approved per Kevin Condie .. 1 year warranty |
Wastewater |
4/02/2012 Corrections required per Kevin Condie.. Concrete around valve's meter box, check wire
4/09/2012 Corrections required per Kevin Condie..Clean and paint turn hydrant, no rebar through box, Fire line valve need to be turned
4/17/12 approved per Kevin C.
3/05/2013 Approved per Kevin Condie .. 1 year warranty |
Engineering |
3/29/2012 Corrections Required Per Brandon Wright..1. File N.O.T. with State of Utah on Swipp 2. Collars are not poured 3. Handicap and stop sign not installed 4. Wall Certifications from Geo tech 5. Letter from Eng on Curb elevation 6. Broken side walk panel on 850 N 7. Warranty Bond with City Wes Jenkins
4/06/2012 Approved per Brandon Wright
9/6/12 - 1 year warranty - approved per Brandon Wright. |
City Development Engineer |
4/2/12 corrections required per Wes Jenkins. Need 10% warranted bond for public improvements.
4/12/2012 Approved per Wes Jenkins
2/06/2013 Approved per Brandon Wright.. 1 year warranty |
Landscaping |
4/2/12 corrections required per Wes Jenkins. Need 10% warranted bond for public improvements.
4/12/2012 Approved Per Wes Jenkins
2/06/2013 Approved per Brandon Wright.. 1 year warranty |
| |