[Blackberry Court -Phase 2]
Number: Grading-43616

Drawing of Record Submitted 3/05/2012
Electronic Drawing 3/05/2012
Final Grading Report 3/05/2012
Date Scheduled 3/8/2012
BUILDING PERMIT RELEASE APPROVALS
Power
Water
Wastewater
Engineering
City Development Engineer
Landscaping
FINAL INSPECTION RELEASE APPROVALS
Power
Water 3/7/2012 Corrections required per Kevin Condie..1. Meter setter on lot#7 and phase 3 by hydrant setter need to be centered in box. 2. 2 setters on lot 11 arc 1" and boxes are 3/4 need 1" boxes looking for some from Sholzens need to be traffic rated 3/9/2012 Approved per Kevin Condie 1/24/2013 Approved per Kevin Comdie.. 1 year wrranty.. Nolan ok w/1" setter in 3/4 heavy boxes 1/21/2014 Approved per Kevin Condie.. 1 year warranty
Wastewater 3/7/2012 Corrections required per Kevin Condie..1. Meter setter on lot#7 and phase 3 by hydrant setter need to be centered in box. 2. 2 setters on lot 11 arc 1" and boxes are 3/4 need 1" boxes looking for some from Sholzens need to be traffic rated 3/9/2012 Approved per Kevin Condie 1/24/2013 Approved per Kevin Comdie.. 1 year wrranty.. Nolan ok w/1" setter in 3/4 heavy boxes 1/21/2014 Approved per Kevin Condie.. 1 year warranty
Engineering 3/12/12 approved per Brandon W. 1/07/2013 Approved per Brandon Wright .. 1 Yr Warranty 1/17/2014 Approved per Brandon Wright.. 2nd Year Warranty
City Development Engineer 3/13/2012 Approved per Wes Jenkins 1/07/2013 Apporved Per Brandon Wright 1 yr warranty
Landscaping 3/13/2012 Approved per Wes Jenkins 1/07/2013 Approved per Breandon Wright
    
General Comments: