[Silkwood Phase 4]
Number: Grading-44122

Drawing of Record Submitted 8/07/2012
Electronic Drawing 8/07/2012
Final Grading Report 7/27/2012
Date Scheduled 8/08/2012
BUILDING PERMIT RELEASE APPROVALS
Power
Water
Wastewater
Engineering
City Development Engineer
Landscaping
FINAL INSPECTION RELEASE APPROVALS
Power
Water 8/9/12 corrections required by Kevin Condie. Lot #44 meterbox is about 1 1/2 to 2" too low - REDO. Crimson Ridge the meter boxes need concrete collars around them. Clean hydrants and paint if needed. Need to check wires. 8/14/2012 Approved per Kevin Condie.. Tim ok w/wire 7/15/2013 AZpproved per Kevin Condie.. 1 year warranty
Wastewater 8/9/12 corrections required by Kevin Condie. Lot #44 meterbox is about 1 1/2 to 2" too low - REDO. Crimson Ridge the meter boxes need concrete collars around them. Clean hydrants and paint if needed. Need to check wires. 8/14/2012 Approved per Kevin Condie.. Tim ok w/wire 7/15/2013 AZpproved per Kevin Condie.. 1 year warranty
Engineering 8/9/2012 Corrections Required Per Brandon Wright..Bond for public improvements and sidewalks, grout DI box along shelf 8/16/2012 Approved per Brandon Wright 7/8/13 - 1 year warranty - approved per Brandon Wright.
City Development Engineer 8/15/2012 Approved For Streets Dept,ONLY Per Ed Welch 8/16/2012 Approved per Wes Jenkins 7/8/13 - 1 year warranty - approved per Brandon Wright.
Landscaping 8/16/2012 Approved per Wes Jenkins 7/8/13 - 1 year warranty - approved per Brandon Wright.
    
General Comments: