Drawing of Record Submitted |
|
Electronic Drawing |
|
Final Grading Report |
|
Date Scheduled |
|
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
3/9/04. PERMITS ONLY APPROVED per Zene. No tieing on till ALL streets are paved with M/H's raised and collared.
3/16/04 - PERMITS ONLY - corrections required per Jeff Lance. Not ready for permits.
3/25/04 - PERMITS ONLY - okay per Kevin Condie. |
Wastewater |
3/9/04. PERMITS ONLY APPROVED per Zene. No tieing on till ALL streets are paved with M/H's raised and collared.
3/16/04 - PERMITS ONLY - corrections required per Jeff Lance. Not ready for permits.
3/25/04 - PERMITS ONLY - okay per Kevin Condie. |
Engineering |
3/9/04. for PERMITS ONLY - Corrections required per Larry Henderson. Need to lay base for all weather road.
3/23/04. Approved for PERMITS ONLY per Mike Hester |
City Development Engineer |
3/9/04. for PERMITS ONLY - approved per Judd Burgess. |
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
|
Water |
4/30/04 corrections required per Kevin Condie. Raise 2 fire hydrants. Break off two meter collars. Raise 1 valve. Paint bottom of hydrant. Valve extension on deep valves.
05/19/04. Approved per Boyd Roundy,for final. |
Wastewater |
4/30/04 corrections required per Kevin Condie. Raise 2 fire hydrants. Break off two meter collars. Raise 1 valve. Paint bottom of hydrant. Valve extension on deep valves.
05/19/04. Approved per Boyd Roundy,for final. |
Engineering |
4/16/04 - corrections required per Larry Henderson. Replace broken sidewalk. Build 10' wide gravel shoulders on Havasu and Bluegrass. Patch cracked curb. Trim expansion joints. Fix inlet grate on Summer Poppy. Repaint rusty inlet grates.
4/23/04 approved per Larry Henderson. |
City Development Engineer |
4/15/04 approved per Judd. |
Landscaping |
4/15/04 - approved per Mark Bradley - N/A. |
| |
General Comments: |
Dust a concern for adjacent church. Grading Permit requires control of dust during grading operations. Grading Fees $727.50. |