| Drawing of Record Submitted | 1/28/2013 |
|---|---|
| Electronic Drawing | 1/28/013 |
| Final Grading Report | 1/24/2013 |
| Date Scheduled | 1/31/2013 |
| BUILDING PERMIT RELEASE APPROVALS | |
| Power | |
| Water | |
| Wastewater | |
| Engineering | |
| City Development Engineer | |
| Landscaping | |
| FINAL INSPECTION RELEASE APPROVALS | |
| Power | 1/31/2013 Approved per Dennis Wright 1/9/13 - 1 year warranty - approved per Dennis Wright. |
| Water | 2/1/13 corrections required per Carson Tait. Need a concrete pad poured around the meter box. Need the backflow assemblies tested and tagged. (2) one outside and the assembly on the fireline riser. 2/20/13 approved per Carson T. 1/10/2014 Approved per Carson Tait.. 1 year warranty |
| Wastewater | 2/1/13 corrections required per Carson Tait. Need a concrete pad poured around the meter box. Need the backflow assemblies tested and tagged. (2) one outside and the assembly on the fireline riser. 2/20/13 approved per Carson T. 1/10/2014 Approved per Carson Tait.. 1 year warranty |
| Engineering | 1/31/13 corrections required per Brandon W. Asphalt will not drain properly to East side of lot. Striping is not complete. 2/19/13 approved per Brandon W. 1/14/2014 Approved per Brandon Wright.. 1 year warranty |
| City Development Engineer | 1/31/13 STREETS - approved per Randy Halverson. 2/1/13 corrections required per Wes Jenkins. Asphalt needs to be addressed. 2/19/13 approved per Brandon W. |
| Landscaping | 2/1/13 approved per Craig H. |
| General Comments: | |