[Hidden Valley Townhomes]
Number: Grading 28271

Drawing of Record Submitted 08/24/2004
Electronic Drawing
Final Grading Report 08/19/04--addition 09/21/2004
Date Scheduled
BUILDING PERMIT RELEASE APPROVALS
Power
Water 3/10/04 - PERMITS ONLY - correction required per Zene. Need job to get farther along. 4/23/04 approved PERMITS ONLY per Kevin Condie.
Wastewater 3/10/04 - PERMITS ONLY - correction required per Zene. Need job to get farther along. 4/23/04 approved PERMITS ONLY per Kevin Condie.
Engineering Original Permit was issued Sept. 20, 02` The development has been changed as to layout, elevations, etc. Quality Excavation is grading contractor. The original permit will be used as current permit for grading. A LDS Church site outside the Southwest corner of the development site will be graded with material from the Hidden Valley development but will require a seperate permit. 3/10/04 - PERMITS ONLY - corrections required per Mike Hester. Must complete all public improvements (not private). Complete all utilities and drainage. Provide an all weather access and fire protection. 3/23/04. Corrections required for PERMITS ONLY per Mike Hester. Complete all weather accesses. 4/22/04 - PERMITS ONLY - approved per Mike Hester.
City Development Engineer 3/10/04 - PERMITS ONLY - corrections required per Catherine Hasfurther. Public improvements. Drainage. All weather access. 4/22/04 approved PERMITS ONLY per Cathy Hasfurther.
Landscaping
FINAL INSPECTION RELEASE APPROVALS
Power
Water 08/25/2004 Approved per Carson tait. Need one valve box lid. Need to clean the concrete off of the valve box lids on Brigham Road. 10/15/2004 Approved for Phase 2 and 3 only .. Not ready for phases 4 and 6. Re-inspection required on 4 and 6.
Wastewater 08/25/2004 Approved per Carson tait. Need one valve box lid. Need to clean the concrete off of the valve box lids on Brigham Road. 10/15/2004 Approved for Phase 2 and 3 only .. Not ready for phases 4 and 6. Re-inspection required on 4 and 6.
Engineering 08/25/2004 Corrections required Per Mike Hester. 1. Clean S>D> inlets. 2. Clean all public improvements. 3. COmplete or Bond for all landscaping. 4. Remove all construction debris. 5. Pour the sidewalk for the school x-ing. 6. Complete all monumentation. 7. Backfill all sidewalk and trenches. 8. Remove the prime from the north end of the roadway island.9. Address signs and directory board.10. Rip Rap and grade the EP shoulders. 09/02/2004 Approved per Mike Hester 10/13/2004 Approved per Mike Hester for Phase 2-3 only.. Phase 4 needs 1. Landscape and walls constructed.. Complete the detention basins, Clean all public improvements.
City Development Engineer 09/03/2004 Approved per Cathy Ok Phase 1 only.. 11/05/2004 Approved per Cathy Hasfurther for phase 2 and 3 only.. Electronic Dg of record.
Landscaping 08/23/2004 N/A... Parks to check with C.O. Doug- Street Trees Insp. Landscape around bldg.
    
General Comments: