| Drawing of Record Submitted | 6/30/2014-7/16/2014 |
|---|---|
| Electronic Drawing | 6/30/2014-7/16/2014 |
| Final Grading Report | 6/30/2014-7/16/2014 |
| Date Scheduled | 7/03/2014-7/17/2014 |
| BUILDING PERMIT RELEASE APPROVALS | |
| Power | |
| Water | |
| Wastewater | |
| Engineering | |
| City Development Engineer | |
| Landscaping | |
| FINAL INSPECTION RELEASE APPROVALS | |
| Power | |
| Water | 7/01/2014 Corrections required per Kevin Condie.. Phase 1 ok Need to Final Desert Canyon Drive First 7/18/2014 Approved per Kevin Condie 7/08/2015 Approved per Kevin Condie 1 year warranty |
| Wastewater | 7/01/2014 Corrections required per Kevin Condie.. Phase 1 ok Need to Final Desert Canyon Drive First 7/18/2014 Approved per Kevin Condie 7/08/2015 Approved per Kevin Condie 1 year warranty |
| Engineering | 7/03/2014 Corrections Required Per Brandon Wright.. Not ready for Final 7/18/2014 Approved per Brandon Wright..NOTE: Concrete Islands need to be poured at roundabout before 1 year warrant, Note: Wes Jenkins is working Rockwall problems out with Quality 5/22/2015 Approved per Brandon Wright 1 year warranty |
| City Development Engineer | 4/08/2014 Approved per Jared Stewart STREETS DEPT Only.. Signs ok |
| Landscaping | 7/2/14 Corrections required per Craig Harvey. Install landscaping as shown on plan or bond for the improvements. 8/06/2015 Approved per Craig Harvey Parks Dept Per Craig Harvey.. 1 year warranty Note: For Deserts Edge Drive Trail |
| General Comments: | |