Drawing of Record Submitted |
6/02/2014 |
Electronic Drawing |
6/02/2014 |
Final Grading Report |
6/02/2014 |
Date Scheduled |
6/30/2014 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
|
Water |
6/27/2014 Approved per Kevin Condie.. Handle on meter setters is missing, clean & paint hydrant,
6/1/2015 Approved per Kevin Condie 1 yr warranty |
Wastewater |
6/27/2014 Approved per Kevin Condie.. Handle on meter setters is missing, clean & paint hydrant,
6/1/2015 Approved per Kevin Condie 1 yr warranty |
Engineering |
6/25/14 corrections required per Brandon Wright. Northwest inlet office plate not connected to wall needs to be fixed. Striping not complete. Signs missing for handicap stalls. Missing stop signs. Clean up on city street needed.
7/15/2014 Approved per Brandon Wright
5/19/15 1 yr warranty approved per Brandon Wright |
City Development Engineer |
6/27/2014 Approved Per Streets Dept Jared Stewart
7/02/2014 Corrections required per Wes Jenkins.. Need to Finish landscaping as shown on the approved construction drawings
7/15/2014 Approved per Wes Jenkins |
Landscaping |
7/2/14 corrections required per Wes Jenkins - Need to finish landscaping as shown on the approved construction drawings.
7/11/2014 Approved per Craig Harvey Number of dead shrubs are dead, however the FM grove will be replacing them in the fall after the temperature drops to the 80's |
| |
General Comments: |
|