| Drawing of Record Submitted | 11/01/2013 11/12/2013 |
|---|---|
| Electronic Drawing | 11/01/2013 11/12/2013 |
| Final Grading Report | 11/01/2013 |
| Date Scheduled | 11/05/2013 |
| BUILDING PERMIT RELEASE APPROVALS | |
| Power | |
| Water | |
| Wastewater | |
| Engineering | |
| City Development Engineer | |
| Landscaping | |
| FINAL INSPECTION RELEASE APPROVALS | |
| Power | 11/14/2013 Approved per Dennis Wright.. Note: One transformer needs to be changed out will be done at late date 12/29/2014 Approved per Dennis Wright 1 year warranty |
| Water | 11/15/2013 Approved per Carson Tait. 1/12/2015 Approved Per Kevin Condie 1 yr Warranty |
| Wastewater | 11/15/2013 Approved per Carson Tait. 1/12/2015 Approved Per Kevin Condie 1 yr Warranty |
| Engineering | 11/12/2013 Approved per Brandon Wright 1/08/2015 Approved per Brandon Wright 1 year warranty |
| City Development Engineer | 11/06/2013 Approved per Jared Stewart.. Streets Dept 12/9/13 approved per Wes Jenkins. |
| Landscaping | 12/9/13 approved per Wes Jenkins. |
| General Comments: | |