| Drawing of Record Submitted | 11/04/2014 |
|---|---|
| Electronic Drawing | 11/04/2014 |
| Final Grading Report | |
| Date Scheduled | 11/13/2014 |
| BUILDING PERMIT RELEASE APPROVALS | |
| Power | |
| Water | |
| Wastewater | |
| Engineering | |
| City Development Engineer | |
| Landscaping | |
| FINAL INSPECTION RELEASE APPROVALS | |
| Power | 11/13/2014 Approved Per Dennis Wright 11/18/2015 approved per Jeremie Higgins |
| Water | 11/14/2014 Corrections required per Brad Drummond.. Needs cement around meter boxs and fire hydrant, back flow assemblies need to be tested landscaping outside, fire riser inside 11/19/2014 Corrections required Per Brand Drummond..Concrete is good outside back flow assembly has been tested back flow at fire riser needs to be tested still 11/21/2014 Approved per Brad Drummond 12/2/15 approved |
| Wastewater | 11/14/2014 Corrections required per Brad Drummond.. Needs cement around meter boxs and fire hydrant, back flow assemblies need to be tested landscaping outside, fire riser inside 11/19/2014 Corrections required Per Brand Drummond..Concrete is good outside back flow assembly has been tested back flow at fire riser needs to be tested still 11/21/2014 Approved per Brad Drummond 12/2/15 approved |
| Engineering | 11/19/2014 Approved per Brandon Wright 11/20/2015 Approved 1 yr warranty per Brandon Wright |
| City Development Engineer | 11/13/2014 Streets Dept Only.. NEED 10% Warranty Bond 11/20/2014 Approved per Wes Jenkins Rcvd Bond |
| Landscaping | 11/13/2014 Corrections required per John Willis Street Trees are not installed per Old approved Plans 11/20/2014 Approved per John Willis |
| General Comments: | |