| Drawing of Record Submitted | 7/11/2014 |
|---|---|
| Electronic Drawing | 7/14/2014 |
| Final Grading Report | 7/14/2014 |
| Date Scheduled | 7/16/2014 |
| BUILDING PERMIT RELEASE APPROVALS | |
| Power | |
| Water | |
| Wastewater | |
| Engineering | |
| City Development Engineer | |
| Landscaping | |
| FINAL INSPECTION RELEASE APPROVALS | |
| Power | |
| Water | 7/17/2014 Corrections required per Kevin Condie.. Cut plastic off of bottom of Fire hydrant & paint bottom of hydrant & hydrant if needed open all valves 7/22/2014 Approved per Kevin Condie |
| Wastewater | 7/17/2014 Corrections required per Kevin Condie.. Cut plastic off of bottom of Fire hydrant & paint bottom of hydrant & hydrant if needed open all valves 7/22/2014 Approved per Kevin Condie |
| Engineering | 7/16/2014 Approved per Brandon Wright |
| City Development Engineer | 7/16/2014 Approved Per Jared Stewart Streets Dept Only 8/04/2014 Approved per Wes Jenkins |
| Landscaping | 8/04/2014 Approved per Wes Jenkins |
| General Comments: | |