Drawing of Record Submitted |
02/08/2006 |
Electronic Drawing |
02/08/2006 |
Final Grading Report |
02/09/2006 |
Date Scheduled |
02/14/2006 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
02/15/2006 Approved per Dennis Wright
2/4/2008 Approved per Dennis Wright.. 1 yr warranty |
Water |
02/14/2006 Corrections required per Kevin Condie.. Last inspection was in June. Remove all concrete from around valve collars. Need Bac-T. Meter setter's on rolled curb that doesn't have sidewalk, need to be 18" to 24" Behind curb. Need to check wire and finish @ sidewalk and collers. No rep from Quality was there.
3/7/06 - Corrections Required per Kevin Condie - All meter boxes need collars around them. Fix broken concrete collars. Clean and paint hydrants. Fire hydrant test outside phase line. Need valve can. There are about 4 services that need to be lowered. Fire hydrant at lot 48 need some dirt behind it so it doesn't blow off. There is two boxes broken at lot 33, 32. All fire hydrants need concrete around them. Diamon block around meter setter boxes. All need to check wire. (NOT READY).
03/14/2006 Approved per Kevin Condie |
Wastewater |
02/14/2006 Corrections required per Kevin Condie.. Last inspection was in June. Remove all concrete from around valve collars. Need Bac-T. Meter setter's on rolled curb that doesn't have sidewalk, need to be 18" to 24" Behind curb. Need to check wire and finish @ sidewalk and collers. No rep from Quality was there.
3/7/06 - Corrections Required per Kevin Condie - All meter boxes need collars around them. Fix broken concrete collars. Clean and paint hydrants. Fire hydrant test outside phase line. Need valve can. There are about 4 services that need to be lowered. Fire hydrant at lot 48 need some dirt behind it so it doesn't blow off. There is two boxes broken at lot 33, 32. All fire hydrants need concrete around them. Diamon block around meter setter boxes. All need to check wire. (NOT READY).
03/14/2006 Approved per Kevin Condie |
Engineering |
02/14/2006 Corrections required per Larry Henderson.. Backfill behind sidewalk and curb,finish sidewalk, finish water meter collars,clean up lots and finish to grade, make curb @ corners handicap accessable, cleanout inlet boxes, stamp monuments
03/06/2006 Corrections required per Larry Henderson.. Punched list items not done..
03/13/2006 Corrections required per Carlos Robles.. Ramp off sidewalks,trim down expansion joint papers, clean road and walks.
03/14/2006 Approved per Carlos Robles |
City Development Engineer |
02/24/2006 Corrections required per Wes Jenkins..1. Finish sidewalk at lots 47,48,57, and 62..2. Install handicap ramp per approved construction drawings at lot 54.3. Provide 10% warrranty bond for all improvements except those along Tonaquint Drive. 4. Provide private improvment development development certificate.
03/10/2006 Corrections required per Cathy H. 1. Provide 10% warranty bond for all improvement except for Tonaquint Dr. 2.Complete S/W. 3. Clean streets. 4. Concrete collar water meter boxes and FH, 5. Provide private development certificate improvement. 6. Complete retainig walls per plan.
03/14/2006 Phase is released for PERMITS ONLY..per Matt Loo
2/28/07 Corrections required per Ken B. Building material on sidewalk. End of road markers missing. Sidewalks damaged and requires replacing. Asphalt spauling and pitting. Streets are sunken in with water standing. Curbing is chipped out in several locations and needs replaced. Linear cracks in asphalt. Heavy equipment marks in asphalt.
3/7/07 Approved per Cathy H.
2/7/2008 Approved per Ken Bricker 1 yr warranty..Look tosee s/w & landscaping and wall are installed along Tonquint Dr |
Landscaping |
02/15/2006 Corrections required per Mark Bradley.. Tonaquint Drive improvements. privacy wall, street trees and landscape, complete sidewalks.
03/09/2006 Approved per Mark Bradley.. See NOTES: City is constructing Tonaquint Drive. A bond for the improvements and landscapine along Tonaquint Drive has been posted with Wes Jenkins. The privacy wall is to be constructed with the homes at this point. Required prior to the CO of homes along Tonaquint Drive. I told Jair with Salisbury Homes to start at Southend and move North.
2/7/2008 Approved per Ken Bricker 1 yr warranty.. Look to see s/w & landscaping and wall are installed along Tonaquint Dr |
| |
General Comments: |
|